Serfis Construction and Engineering appointed Principal Contractor to undertake the resurfacing of the 3200m2 car park correcting variations in levels and installing the required line markings.

Client: Transport for West Midlands
Job: Remove & relay road
Our Involvement

Serfis Construction and Engineering attended site as agreed with the client during a 5-day closure proceeding to remove the deteriorating surface, relay a new surface course, reinstate the speed humps, and reline the carpark throughout.

Problems Faced / Solutions Offered

Our client allocated a maximum five- day window for the works to be completed. Timed deliveries/ collections were crucial to ensure the car park was open reopened on time for its users.

Summary

The work was completed ahead of schedule leaving a quality finish with the surface levels checked and running correctly following the works.